A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work is further increased by 50%

  1. 24
  2. 21
  3. 18
  4. 15
Show answer

Answer: D. 15

Solution

  1. 7⁄8 of the job takes 21 days, so 1⁄8 takes 3 days and the full job takes 24 days.
  2. The work is increased by 50%, so the total work = 1.5 jobs = 12⁄8.
  3. Work done = 7⁄8; remaining = 12⁄8 − 7⁄8 = 5⁄8.
  4. Time for 5⁄8 = 5 × 3 = 15 days.
  5. Check: 21 + 15 = 36 days = 1.5 × 24. ✓

Why the other options are wrong

  • (a) 24: the time for one whole job, not the remaining work.
  • (b) 21: the time already spent on 7⁄8 of the job.
  • (c) 18: 6⁄8 of the job, which assumes 1⁄8 more than is left.

Quick trick

  • Count in eighths at 3 days each: total 12 eighths, 7 done, 5 left → 15 days.

Remember

Convert work to equal units, find the time per unit, then multiply by the units left.

Hence the answer is (d).

Share
Ask Atlas (5) for similar questions
  1. 2022 · Q57 Time Work Data Inadequate — Same work-and-workers pattern, scaling men and women to find days needed.
  2. 2020 · Q60 Time Work Complete Together — Same concept: work expressed as percentages and days, combined work for a target fraction.
  3. 2025 · Q69 Time Work Complete Certain — Same fractional-work idea: partial work done by several workers over days, remaining work finished.
  4. 2024 · Q7 Time Work Certain Complete — Same work-rate idea: change in amount of work or workers to change completion time.
  5. 2023 · Q30 Time Work Monday Tuesday — Same work-rate basis: days for individual workers to complete a whole job.

← Full UPSC CSE 2021 CSAT paper · All Basic numeracy questions